 Post subject: HASP 2010 Schedule
PostPosted: Fri Feb 05, 2010 12:33 pm 
Offline
Site Admin

Joined: Wed Mar 04, 2009 6:05 pm
Posts: 96
Location: Baton Rouge, La
Monthly Status Reports: A status report from the student team lead will be due on the last day of the month from January through November. This is a brief report, no longer than one or two pages, that describes for the month 1) activities of the team members, 2) issues encountered during payload design / development, 3) milestones achieved and 4) current team members and leaders. The report should be e-mailed to guzik@phunds.phys.lsu.edu and can be in either MS Word 2003 or PDF format. These reports are due on the last Friday of every month.

Monthly Teleconference Meetings: A “meet-me” teleconference will be held each month from February through December. At least the Faculty Advisor and Team Leader should be present at the teleconference, but we encourage all team members to participate. The teleconferences will be held on the first Friday of every month at 10:00 am (central time) [11 am eastern, 9 am mountain, 8 am pacific]. To participate dial in to 1-866-717-2684 prior to the conference time. When requested enter the Conference ID number 6879021 followed by the # key.


DATETOPIC
January 29Monthly status report due
February 5Monthly teleconference at 10 am (central time)
February 26Monthly status report due
March 5Monthly teleconference at 10 am (central time)
March 26Monthly status report due
April 2Monthly teleconference at 10 am (central time)
April 23Preliminary Payload Specification & Integration Plan (PSIP) due
April 30Monthly status report due
May 7Monthly teleconference at 10 am (central time)
May 24 to 28Preliminary HASP thermal / vacuum testing at CSBF
May 28Monthly status report due
June 1Final Payload Specification & Integration Plan (PSIP) due
June 4Monthly teleconference at 10 am (central time)
June 25Monthly status report due
July 2Monthly teleconference at 10 am (central time)
July 30Monthly status report due
August 1Final Flight Operation Plan (FLOP) due
August 2 to 6Student payload integration with HASP & thermal / vacuum testing
August 13Monthly teleconference at 10 am (central time) Note date!
August 27Monthly status report due
*August 29Begin HASP flight preparation at Ft. Sumner, NM
*September 1Students supporting flight line ops arrive at Ft. Sumner, NM
*September 3Target HASP flight ready date
September 3Monthly teleconference at 10 am (central time)
*September 6Target HASP launch and flight operations date
*September 8 to 11Recovery, packing and return shipping
September 24Monthly status report due
October 1Monthly teleconference at 10 am (central time)
October 29Monthly status report due
November 5Monthly teleconference at 10 am (central time)
November 30Monthly status report due Note date!
December 3Monthly teleconference at 10 am (central time)
December 17Final Flight / Science Report due


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 1 post ] 

All times are UTC - 6 hours [ DST ]


Who is online

Users browsing this forum: Google [Bot] and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Group