LSU crew will be traveling to Fort Sumner, New Mexico over the next few days in order to begin HASP 2012 flight operations next week. Critical milestone dates are as follows:

Monday, August 27 -- HASP setup and integration with CSBF
Wednesday, August 29 -- Configuration and testing of student payloads
Friday, August 31 -- HASP "hang test" and Flight Readiness Review
Monday, September 3 -- Target launch date

Details about these events and the HASP 2012 students payloads will be provided here as flight operations progress.

T.G. Guzik


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 1 post ] 

All times are UTC - 6 hours [ DST ]


Who is online

Users browsing this forum: No registered users and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Group