HASP Technical Documentation
HASP -- Time and Position
Data String Serial Latency Measurements
(PDF
Version): GPS time and position
data is now available to student payload groups via serial communication. They can request
to receive these data strings from the HASP flight system at some pre-defined period, specified
prior to integration. The string contains a timestamp and GPS coordinate information. The GPS
coordinate information could alleviate the need for groups to purchase and deploy their own GPS
system which could reduce the costs of student payloads both in materials and development time.
The timestamp generated by HASP is accurate to within 1 millisecond and might be used by the payload
as an accurate clock. However, there is a latency introduced by the serial communication. The
current version of this document is dated 02/16/2009.
HASP -- Student
Payload Interface Manual (PDF
Version): This document
describes the basic features of the HASP payload mounting plate and provides
information on the mechanical, electrical, power and data interfaces.
Further, the document provides some suggestions for how to use the discrete
command channels, downlink telemetry and uplinked serial commands. The
current version of this document is dated 02/17/2009.
HASP Payload
Specification and Integration Plan Template (MS
Word Version): Student teams fill out this template to provide
technical details on the final flight configuration of the payload including
measured weights, measured current draw (@30 VDC), downlink data format and
rate, uplink commands, analog output usage, discrete command usage, and
dimensioned mechanical drawings. In addition, the student teams plans for
integration with with HASP should be detailed including, at least, all test
procedures and test procedure validation results, requested test equipment,
schedule and personnel participating in integration. The current version
of this template is dated 09/11/2007.
HASP Payload
Integration Certification Template (PDF
Version): At integration all interfaces will be documented and
validated, correct operation of the payload will be verified and any issues
identified will be detailed. This certification document will be handled
by HASP management during integration. Note that you will not be able to
fly until this certification is complete. The current version of this
template is dated 02/11/08.
HASP Flight
Operation Plan Template (MS
Word Version): Student teams fill out this template to detail
procedures for flightline setup, pre-launch checkout, flight operations, error
recovery, safeing and payload recovery including a timeline showing specific
events relative to the launch at T=0 and identifying personnel participating in
flight operations. Note that any operations requested to be performed by
HASP flight personnel other than the power-up ~one hour prior to launch (T - 1
hr) and power down prior to terminate must be specified in this document.
The current version of this template is 09/11/2007.